WE Report

Lessons Learned

Lesson Learned





By: Drilling Engineer

Report No.

2321

Discipline/Origin

Drilling
Own Experience

Well

Hemispheres
36/1-4

Date created

2021/12/23
1444 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Casing
Positive

Borgland Dolphin


What happened in Top hole:
o At 281m conductor couldn’t pass due to the tight spot observed when drilling there. Attempted to work the string with 5-10 MT down weight and skidded rig 10m in every direction. Did this for 2.5 hrs. In the end, the down weight were increased to 20 MT. When we were about to POOH with conductor, the rig was skidded above well centre, still applying 20 MT down weight, and suddenly the conductor passed the restriction.

What Was Planned

Run 30″ conductor to TD of 307 meter. It was during drilling of 36″ hole observed slow drilling and tight spot at 282-283m.

What Was Learned

That applying steady down weight at the tight spot while skidding rig is a possibility to pass restriction.

What Actions Are Required

Since this was a tight spot observed while drilling, we could have just reamed through that small interval when POOH once.